JPL ANALYSIS REPORT GPS-WEEK 0748 (DAYS 128-134, DATES 1994 May 08 - May 14)
******************************************************************************
Submitted by the JPL IGS/FLINN Analysis Team:
J F Zumberge, D C Jefferson, M B Heflin, M M Watkins, F H Webb
all at the Jet Propulsion Laboratory, California Institute of Technology,
Pasadena, CA 91109.
Files listed below are available in Unix compressed format and can be
retrieved using anonymous ftp to sideshow.jpl.nasa.gov (128.149.70.41),
directory pub/jpligsac/0748. These files have also been sent to the CDDIS.
______________________________________________________________________________
filename contents
______________________________________________________________________________
jpl07487.sum This text file.
jpl07487.erp Earth rotation parameters for GPS week 748.
jpl0748[0-6].sp3 GPS ephemerides for GPS week 748, sp3 format.
______________________________________________________________________________
Including BRMU in the solution for days 129 and 130 (May 9, 10) caused
atypically high clock repeatability values on their respective previous days
(May 8, 9). Also, the inclusion of RCM5 caused an excessive number of outliers
in our solutions for days 131 and 132 (May 11,12). We have excluded these
sites from our analyses on the corresponding days.
We continue to exclude data from WEST; see IGS Mail Message 585 for details.
Also, according to IGS Mail Message 597, the receiver at VNDP was replaced on
day 133 (May 13). Data from this site was not available for this or subsequent
days of this week at the time of processing.
As noted in several of our recent analysis reports, it has been necessary
to exclude NLIB on numerous days of processing. We understand that poor
performance at this site is possibly being caused by a faulty receiver cable.
We have chosen to delete data from NLIB indefinitely, pending further notice
that the data from this site are consistently usable.
WARNING: Data from NLIB and WEST excluded for the entire GPS week 748.
WARNING: Data from BRMU excluded days 129 and 130 (May 9, 10).
WARNING: Data from RCM5 excluded days 131 and 132 (May 11, 12).
WARNING: No data from VNDP days 133 and 134 (May 13, 14).
JPL LODR TABLE GPS week 748 (1994 May 08 - May 14)
MJD LODR +/-
(ms/day)
49480.5 2.45 0.02
49481.5 2.45 0.01
49482.5 2.41 0.01
49483.5 2.47 0.01
49484.5 2.43 0.01
49485.5 2.46 0.01
49486.5 2.42 0.01
END LODR TABLE
NOTE: In the following table, UT1R-UTC are the assumed nominal values from
IERS Bulletin-B predicts; estimated LODR values are given in the previous
table. See IGS Mail Message 97 for details.
JPL UTPM TABLE GPS week 748 (1994 May 08 - May 14)
MJD X Y UT1R-UTC XSIG YSIG UTSIG RMS XYC XUC YUC STA SAT PASS
'' '' sec '' '' sec
49480.5 .18654 .31822 -.11441 .00015 .00013 .00000 .0 -.04 .00 .00 44 25 0
49481.5 .18705 .31588 -.11692 .00010 .00011 .00000 .0 .09 .00 .00 43 25 0
49482.5 .18775 .31368 -.11941 .00009 .00010 .00000 .0 .03 .00 .00 41 25 0
49483.5 .18829 .31203 -.12190 .00009 .00012 .00000 .0 .00 .00 .00 41 25 0
49484.5 .18897 .31019 -.12438 .00008 .00009 .00000 .0 .02 .00 .00 42 25 0
49485.5 .18942 .30789 -.12685 .00008 .00009 .00000 .0 -.04 .00 .00 42 25 0
49486.5 .18929 .30601 -.12932 .00009 .00009 .00000 .0 -.01 .00 .00 41 25 0
END UTPM TABLE
The following table indicates the "3-dimensional orbit repeatability", as
defined in IGS Mail Message 37, for GPS week 748:
["3d rss" = sqrt(xrms**2 + yrms**2 + zrms**2)]
JPL ORBIT REPEATABILITY TABLE GPS week 748 (1994 May 08 - May 14)
94 5 8 94 5 9 94 5 10 94 5 11 94 5 12 94 5 13 94 5 14
prn 3d rss (m)
1 0.78 0.76 0.82 0.77 0.90 0.85 0.97
2 0.77 0.50 0.64 0.58 0.72 0.71 0.47
4 0.46 0.49 0.46 0.36 0.55 0.55 0.56
5 0.39 0.32 0.32 0.40 0.34 0.44 0.40
6 1.33 0.86 0.76 0.75 0.80 1.46 1.43
7 1.04 1.64 1.39 1.11 1.28 1.15 1.21
9 1.02 1.03 0.87 1.02 1.21 1.26 1.20
12 0.45 0.29 0.32 0.36 0.37 0.35 0.31
14 0.49 0.84 0.35 0.48 0.20 0.35 0.28
15 0.65 0.92 0.56 1.18 0.80 0.66 0.81
16 0.41 0.36 0.23 0.22 0.33 0.43 0.38
17 1.29 1.12 0.91 0.85 0.89 0.85 0.96
18 0.6 0.33 0.71 0.56 0.33 0.59 0.46
19 1.03 0.80 0.80 0.71 0.76 1.01 0.79
20 0.75 0.43 0.41 0.31 0.42 0.33 0.43
21 0.25 0.24 0.52 0.69 0.47 0.36 0.60
22 0.41 0.69 0.50 0.40 0.41 0.48 0.43
23 0.27 0.33 0.47 0.35 0.39 0.13 0.39
24 0.48 0.37 0.48 0.46 0.43 0.55 0.51
25 0.88 1.20 0.76 0.72 0.59 0.92 1.16
26 0.67 0.83 0.69 0.66 0.71 0.60 0.98
27 0.93 0.62 0.75 0.58 0.75 0.86 0.72
28 0.68 0.68 0.87 1.02 0.82 0.81 0.59
29 0.45 0.33 0.33 0.72 0.37 0.40 0.32
31 0.53 0.68 0.69 0.77 0.77 0.63 0.65
_______________________
END ORBIT REPEATABILITY TABLE
As described in IGS Mail Message 37, the following table compares the JPL
precise ephemerides with those from the broadcast ephemeris:
JPL COMPARISON OF BROADCAST NAVIGATION MESSAGE WITH PRECISE EPHEMERIDES
94 5 8 94 5 9 94 5 10 94 5 11 94 5 12 94 5 13 94 5 14
prn 3d rss (m)
1 10.5 9.7 9.8 9.6 8.7 8.1 6.9
2 5.1 4.7 4.4 4.4 3.0 3.6 4.3
4 8.0 8.2 8.2 9.0 8.6 10.4 11.5
5 3.3 3.9 4.1 4.3 3.5 2.7 2.8
6 6.3 7.2 7.7 6.5 6.6 6.8 5.9
7 10.1 10.1 10.3 9.8 9.6 8.7 7.3
9 3.6 5.1 4.5 3.4 3.9 5.1 5.3
12 2.8 3.0 1.9 2.9 3.3 3.7 2.2
14 4.7 4.1 3.6 4.0 4.3 4.6 4.4
15 7.8 5.2 4.1 3.9 4.5 5.7 4.2
16 4.0 4.2 4.2 6.4 6.2 8.2 6.9
17 4.9 4.0 3.5 4.5 3.4 3.8 4.2
18 6.9 8.1 9.1 16.5 10.1 9.8 8.3
19 5.5 4.8 3.2 3.6 4.3 6.2 6.0
20 5.9 7.0 6.7 6.3 6.2 6.0 4.7
21 5.0 4.5 3.6 3.4 5.6 4.0 5.5
22 6.1 3.2 3.5 3.0 3.3 4.5 6.1
23 5.3 3.7 4.6 4.6 2.6 3.3 4.5
24 6.4 6.7 6.3 7.5 7.0 6.6 7.9
25 6.0 7.1 5.3 5.2 7.4 10.5 8.7
26 4.0 6.2 5.5 4.9 7.0 5.5 4.1
27 6.6 5.0 6.5 8.7 6.5 7.9 6.6
28 4.2 4.2 4.1 4.4 5.2 5.4 5.6
29 8.5 6.3 29.4 6.0 6.2 8.2 7.7
31 7.1 5.8 5.3 4.8 5.1 5.3 5.4
_______________________
END COMPARISON OF BROADCAST NAVIGATION MESSAGE WITH PRECISE EPHEMERIDES
The following tables, as explained in IGS Report Nos. 99 and 295, indicate the
amount of global network tracking data used in this week's analysis:
JPL SITE SUMMARY TABLE (no. stations) GPS week 748 (1994 May 08 - May 14)
94 5 8 94 5 9 94 5 10 94 5 11 94 5 12 94 5 13 94 5 14
Fiducial 10.4 10.6 10.9 10.5 11.5 11.4 11.6
Total 39.0 38.3 37.4 36.8 38.1 39.0 38.3
END SITE SUMMARY TABLE
JPL GROUND STATION INCLUSION TABLE GPS week 748 (1994 May 08 - May 14)
94 5 8 94 5 9 94 5 10 94 5 11 94 5 12 94 5 13 94 5 14
site % data
ALBH 93 100 102 103 90 105 103
ALGO* 105 104 104 103 93 102 102
AREQ 104 105 105 105 105 105 105
BRMU 103 0 0 58 73 83 100
CHTP 93 89 90 87 86 87 94
DRAO 108 107 107 107 97 107 108
FAIR* 105 105 105 105 106 105 107
FORT 103 104 104 104 103 103 0
GODE 99 98 103 103 98 101 102
GOLD* 83 91 90 85 75 84 79
GRAZ 60 106 106 106 106 107 106
HART* 72 92 93 0 74 35 51
HARV 109 108 110 110 110 108 106
HERS 74 64 59 61 66 68 75
HOBA 104 104 104 106 106 105 105
JPLM 105 106 107 108 99 0 0
KIRU 104 104 0 104 0 94 87
KOKB* 9 43 112 111 113 111 111
KOSG* 87 84 74 87 93 84 92
KOUR 97 98 99 99 100 100 101
MADR* 81 76 63 78 72 69 79
MASP 107 108 108 108 107 108 107
MATE 78 59 59 38 53 68 67
MCMU 113 113 113 114 113 115 116
MDO1 104 107 106 106 105 105 100
METS 73 67 0 38 103 102 104
NYAL 111 113 114 114 114 114 113
ONSA 103 96 102 102 102 102 103
PAMA 80 70 66 0 59 56 68
PIE1 100 103 105 102 102 103 99
QUIN 100 105 104 102 105 102 102
RCM5 106 105 80 0 0 104 106
SANT* 72 38 48 52 80 96 98
STJO 15 26 106 105 95 105 105
TAIW 99 90 81 21 52 93 86
TIDB* 73 66 61 78 92 87 86
TROM* 103 102 100 101 101 101 101
TSKB 105 107 106 106 105 104 104
USUD 102 102 101 102 101 103 97
VNDP 107 109 107 110 99 0 0
WETT* 79 80 70 75 76 77 73
YAR1* 74 70 67 70 82 87 76
YELL* 102 106 103 104 95 105 102
_______________________
*Indicates fiducial site; #indicates deweighted site.
END GROUND STATION INCLUSION TABLE
As described in IGS Report No. 634, the table below indicates the repeatability
of clock solutions for all satellites and stations used in this week's analysis:
JPL CLOCK REPEATABILITY TABLE GPS week 748 (1994 May 08 - May 14)
94 5 8 94 5 9 94 5 10 94 5 11 94 5 12 94 5 13 94 5 14
comp log10(rms/ps)
PRN01 4.0 3.9 4.0 4.1 3.6 4 3.6
PRN02 3.8 4.0 3.6 4 3 4 4
PRN04 3.3 3.8 3.7 4.1 3.8 3 3.6
PRN05 3.6 4.1 4.0 4.0 3.7 3 3.7
PRN06 4.4 4.0 4.3 4.1 3.6 3 3.7
PRN07 4.1 4.1 4.0 3.9 3.8 4 3.7
PRN09 3.9 4.0 4.0 4.2 3.4 4 3.8
PRN12 3.8 3.9 4.1 4.1 3.9 3 4.1
PRN14 4 3.8 4.1 4 4.1 4 4
PRN15 4.0 4.2 4.1 4 4 4 4
PRN16 3.5 3.9 3.7 4.1 3.8 3 3.8
PRN17 4.0 4.2 4.3 4.3 4.3 4 4.4
PRN18 4 4.1 4.0 4.1 3.9 4 3.9
PRN19 3.9 3.9 3.7 3.9 3.8 4 3
PRN20 3.6 3.7 3.9 4.1 3.9 4 3.9
PRN21 4.1 4.1 4.3 4.5 4.3 5 4.4
PRN22 4.1 4.1 3.7 4.0 4.3 4 4.2
PRN23 3.6 3.8 3.9 4.0 3.7 3 3.8
PRN24 3.7 3.7 3.5 4.2 4.2 4 3.8
PRN25 3.8 3.8 4.0 4.1 3.7 3 3.8
PRN26 4.0 3.6 3.8 4.0 3.6 3 3.6
PRN27 3.8 3.4 3.6 4.1 3.3 3 3.2
PRN28 4.0 3.7 3.5 4.0 3.6 4 3.9
PRN29 3.8 4.1 4.1 4.1 4.0 4 3.6
PRN31 4 3.9 3.9 4.2 3.6 4 4.0
ALBH 3.8 3.8 3.9 4.0 3.7 3 3.5
AREQ 4.3 4.0 3.7 4.0 3.9 4 3.7
BRMU 3 4 3.8 3 3.5
CANB 3.6 3.6 3.5 3.7 2.9 4 3.6
CHTP 3.8 4.1 4.0 4.2 3.9 4 4.1
FAIR 3.7 3.8 3.8 4.0 3.5 4 3.7
FORT 4.1 3.9 3.7 3.9 3.1
GODE 3.9 3.8 3.6 3.9 3.6 4 3.6
GOLD 3.6 3.9 3.7 4.0 3.5 4 3.8
GRAZ 4 4.2 4.0 4.3 4.0 4 4.0
HART 3.9 3.8 4 4 3
HARV 4.0 3.9 4.0 4.1 3.7 4 4.0
HERS 4.7 3.8 3.8 4.1 3.9 4 4.2
HOBA 3.9 3.6 3.5 3.7 3.6 4 3.8
JPLM 3.7 3.8 3.7 4.0 4
KIRU 4.1 3 4 3.7
KOKB 3 4 3.7 3.9 3.8 4 3.8
KOSG 3.9 3.4 3.7 4.0 3.5 4 4.1
KOUR 4.4 4.2 4.3 4.0 4.2 4 4.3
MADR 3.5 3.7 3.9 4 3.7 4 3.9
MASP 4.2 4.3 4.1 4.1 2.7 4 3.8
MATE 3.8 3.9 3.9 4 4 4 3.9
MCMU 3.7 3.8 3.8 3.8 3.6 4 3.7
MDO1 3.5 3.9 3.8 4.0 3.8 4 3.9
METS 3.9 4 4 4.2 4 4.2
NALL 4.0 4.3 4.3 4.2 4.0 4 4.1
ONSA 3.7 3.3 3.9 3.8 3.5 4 3.3
PAMA 4.1 3.6 4 4 4 3.6
PENT 3.9 3.8 3.8 4.0 3.4 4 3.8
PIE1 3.4 3.9 3.9 4.1 3.7 4 3.8
QUIN 3.8 4.0 4.0 4.2 3.9 4 4.0
RCM5 3.8 4.0 4 3 3.5
SANT 3.6 4.0 4.0 3.9 3.8 4 3.5
STJO 2 4 3.5 4.0 3.5 3 3.5
TAIS 3.8 3.1 3.8 4 4 4 3.8
TROM 4.1 4.2 3.9 4.3 4.2 4 3.8
TSKB 3.8 3.5 3.8 3.9 3.3 4 3.7
USUD 3.8 2.9 3.4 3.8 3.8 4 3.8
VNDP 3.7 3.9 3.9 4.0 4
WETB 3.7 3.7 3.4 4.0 3.8 4 4.1
YAR1 3.9 3.6 3.5 3.8 3.9 3 3.7
YELL 3.9 3.7 3.7 4.0 3.4 3 3.4
_______________________
END CLOCK REPEATABILITY TABLE