Dear Colleagues,
For your information, there was delay in delivering the final product for GPS week 1881, they were not delivered to CDDIS until February 16th.
We took the decision to delay the delivery of the final IGS product rather than release it without the clock alignment procedure completed. There was a technical issue preventing the completion of the clock alignment procedure. The technical issue was related to problems re-establishing the communication link between the NRL servers and the back-up server in the Amazon cloud, and was resolved on February 16th.
Kind Regards,
Michael Moore
GNSS Scientist | Geodesy
Geodesy and Seismic Monitoring Group | GEOSCIENCE AUSTRALIA
____________________________________________________________
Phone: +61 2 6249 9052
Email: Michael.Moore at ga.gov.au<mailto:Michael.Moore at ga.gov.au> Web: www.ga.gov.au<http://www.ga.gov.au/>
Cnr Jerrabomberra Avenue and Hindmarsh Drive Symonston ACT
GPO Box 378 Canberra ACT 2601 Australia
Applying geoscience to Australia's most important challenges
Geoscience Australia Disclaimer: This e-mail (and files transmitted with it) is intended only for the person or entity to which it is addressed. If you are not the intended recipient, then you have received this e-mail by mistake and any use, dissemination, forwarding, printing or copying of this e-mail and its file attachments is prohibited. The security of emails transmitted cannot be guaranteed; by forwarding or replying to this email, you acknowledge and accept these risks.
-------------------------------------------------------------------------------------------------------------------------
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.igs.org/pipermail/igsmail/attachments/20160219/39aa1882/attachment.html>
More information about the IGSMail
mailing list