[IGSSTATION-2879]: CHPI: station network upgraded, updated site log
David Maggert
dmaggert at unavco.org
Mon Mar 2 10:01:33 PST 2009
******************************************************************************
IGS Station Mail 02 Mar 10:01:33 PST 2009 Message Number 2879
******************************************************************************
Author: David Maggert, UNAVCO
Dear Colleagues,
The network upgrade is now complete at the IGS station Cachoeira Paulista,
Brazil (CHPI). This upgrade will now allow JPL to publish sub-hourly/high-rate
data in addition to the daily and hourly data. The existing ASHTECH UZ-12 GPS
receiver was replaced with another ASHTECH UZ-12 receiver operating with the
same firmware. The new receiver is the following:
3.6 Receiver Type : ASHTECH UZ-12
Satellite System : GPS
Serial Number : ZR220024515
Firmware Version : CQ00
Elevation Cutoff Setting : 0 deg
Date Installed : 2009-02-12T00:00Z
Date Removed : (CCYY-MM-DDThh:mmZ)
Temperature Stabiliz. : none
Additional Information : (multiple lines)
JPL updated the coordinates in section 2 of the site log. The updated site
coordinates are the following:
X coordinate (m) : +4164613.8900
Y coordinate (m) : -4162456.9100
Z coordinate (m) : -2445028.7600
The updated site log has been submitted to the IGSCB. Data publication will
resume in a couple of days.
ftp://igscb.jpl.nasa.gov/pub/station/log/chpi_20090227.log
Modified/Added Sections : 2, 3.5, 3.6
We apologize for the inconvenience this outage may have caused.
Maintenance and operations of the CHPI station is a collaborative effort
supported by JPL, UNAVCO, and the Instituto Nacional de Pesquisas Espaciais
(INPE) with funding provided by NASA's Earth Surface and Interior Focus Area -
Science Mission Directorate.
Best regards,
David Maggert
More information about the IGSSTATION
mailing list