Dear Colleagues,
The ultra-rapid combination for GPS week 2012, DoW 1 Hour 00 failed due to a problem in creating the summary file. This has now been fixed and the products have been uploaded to the global data centres. The delay in submission is approximately 1 hour.
Regards,
Michael Moore
Dr. Michael Moore
GNSS Analysis Team Leader | Geodesy
IGS Analysis Center Coordinator | (Geoscience Australia & MIT)
Geodesy and Seismic Monitoring Group | GEOSCIENCE AUSTRALIA
____________________________________________________________
Phone: +61 2 6249 9052
Email: Michael.Moore at ga.gov.au<mailto:Michael.Moore at ga.gov.au> Web: www.ga.gov.au<http://www.ga.gov.au/>
Cnr Jerrabomberra Avenue and Hindmarsh Drive Symonston ACT
GPO Box 378 Canberra ACT 2601 Australia
Applying geoscience to Australia's most important challenges
Geoscience Australia Disclaimer: This e-mail (and files transmitted with it) is intended only for the person or entity to which it is addressed. If you are not the intended recipient, then you have received this e-mail by mistake and any use, dissemination, forwarding, printing or copying of this e-mail and its file attachments is prohibited. The security of emails transmitted cannot be guaranteed; by forwarding or replying to this email, you acknowledge and accept these risks.
-------------------------------------------------------------------------------------------------------------------------
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.igs.org/pipermail/igsmail/attachments/20180730/e1fdee10/attachment.html>
More information about the IGSMail
mailing list