[IGSMAIL-7627] Delay in Submission of ultra-rapid product GPS week 2001 DoW 2 Hour 00

IGS ACC acc at igs.org
Mon May 14 22:28:11 PDT 2018


Dear Colleagues,
There was a delay in the submission of the ultra-rapid products for GPS
week 2001, DoW 2, Hour 00. The products should now be available for
download from the global IGS data centers.

The ultra-rapid combination failed to submit due to a missing summary file.
This failed to complete due to an error in the script that creates the
satellite eclipsing information. I'm currently investigating why this has
failed.

Kind Regards,
Michael Moore
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.igs.org/pipermail/igsmail/attachments/20180515/12978288/attachment.html>


More information about the IGSMail mailing list